image image image
Industrial Maintenance General Contracting Design/Build Pre-Engineered Metal Buildings Pipeline and Utilities Support Concrete Conveying Hydro-Vacuum Excavation
image image
image Clients Safety Home Testimonials Employment Opportunities Brochure Contact Us

Projects Ongoing

Owner Project Contract Amount
Aux Sable Misc. Maintenance .5 Million
Caterpillar Inc. Misc. Maintenance 2 Million
ExxonMobil Corp. Misc. Maintenance 3 Million
Lyondell Bassel Ind. Misc. Maintenance 2 Million
Midwest Generation Misc. Maintenance 3 Million
Stepan Company Misc. Maintenance 1 Million

Projects Completed

Owner Project Amount Date
Exelon Dresden LPCI 2 Million Jan. 2011
Exelon Dresden Carbon Fiber 2 Million Jan. 2011
ExxonMobil Pipelines Wilmington Office Building .7 Million Dec. 2010
Enbridge Energy Romeoville Spill Response .7 Million Nov. 2010
ExxonMobil NSR Project 10 Million Oct. 2010
Enbridge Energy Southern Lights ROW Repairs 4 Million Oct. 2010
Exelon Dresden Supplemental Workforce Building 2 Million Aug. 2010
Enbridge Energy Southern Access ROW Repairs 2 Million Jul. 2010
Midwestern Contractors/Enbridge Manhattan Station Phase 2.6 Million Jun. 2009
Midwest Generation Ash Pond Liner #3 .6 Million Nov. 2009
Enbridge Energy Normantown Road Project .6 Million Sep. 2009
Midwestern Contractors/Enbridge Flannigan Station Phase #3 .8 Million Apr. 2009
Midwestern Contractors/Enbridge Flannigan Station Phase #2 1.8 Million Mar. 2009
Midwest Generation Ash Pond Liner #1 & #2 1 Million Oct. 2008
ExxonMobil Corp. Gates Security Road 1.2 Million Sept. 2008
ExxonMobil Corp. NSR CH BRU5148 .5 Million Sept. 2008
Midwetern Contractors Flannagan Phase #1 1.1 Million Aug. 2008
Exelon Dresden New Outage Building 1.3 Million Aug. 2008
Lyondell Chemical Cooling Tower Tray Foundations .5 Million Jul. 2008
Lyondell Chemical Plant Drainage Project .2 Million Jun. 2008
Lyondell Chemical Cooling Tower Flumes .6 Million Mar. 2008
Lyondell Chemical Erect Cable Tray Bridges .2 Million Feb. 2008
Exelon Dresden Transporter Haul Path .5 Million Sep. 2007
ExxonMobil Corp. Bridge #4 .3 Million Aug. 2007
Exelon Dresden Security Upgrade .8 Million Apr. 2007
Stepan Chemical T-9 Foundation .2 Million Jan. 2007
Equistar Equistar Monomer Lab .25 Million Nov. 2006
Caterpillar, Inc. Caterpillar Eng. Test Lab 1.8 Million Oct. 2006
Exelon Exelon Fire Training Building 1 Million Jan. 2006
Unity Unity Distribution Office Building 1 Million Jan. 2006
Exelon Dresden Office Remodel 1 Million Aug. 2005
Exxon Mobil ExxonMobil ULSD 1.5 Million Jun. 2005
Caterpillar, Inc. Caterpillar Eng. Office Remodel .5 Million Jan. 2005
Caterpillar, Inc. Caterpillar Employee Entrance .75 Million Jan. 2005
Caterpillar, Inc. Caterpillar New Truck Entrance .75 Million Dec. 2004
Exelon Corp. Dresden Station Security 8 Million Dec. 2004
Dow Chemical Dow Roof Repair .8 Million Apr. 2004
Caterpillar, Inc. Caterpillar Office Remodel .5 Million Dec. 2003
Exxon Mobil ExxonMobil MOGAS 15 Million Nov. 2003
Exelon Dresden Cooling Tower 4 Million Jun. 2003
Caterpillar, Inc. Caterpillar Truck Dock .6 Million Aug. 2003

Projects

image image
image
image image image image image image image image image image
Email: inof@brieserconstruction.com